To use Flow Decision and Flow Switch activities, you have to make sure that you are placing them inside a Flowchart activity. If not placed inside a Flowchart activity, these two activities would not work. In this basic example, it made use of the Flow Decision activity. You will notice that this activity is placed inside the Flowchart activity.
I'm trying to use Flow Decision and Flow Switch activities, but I can't put them in the Sequence? Print
Modified on: Wed, 18 Mar, 2020 at 2:59 PM